Sewage Treatment

West Angelas #2 Upgrade

Project: West Angelas Village Wastewater Treatment Plant 2, 900EP MBR Upgrade.

Location: West Angelas Village, Pilbara, Western Australia.

Treatment Capacity: 900EP, 280kL/day, upgraded from 450EP.

Date Commissioned: May 2014.

Operational Status: Currently operating.

Comments:The upgrade involved installation of a dual train membrane bioreactor and associated infrastructure.

Site time to implement the upgrade was 12 days from mobilisation to commissioning and was sequenced to allow the plant to continue to treat the influent load during the upgrade.

The upgraded plant was commissioned with influent sewage and was immediately compliant.