Sewage Treatment

Weelumurra Village

Project: Weelumurra Village Waste Water Treatment Plant.

Location: Weelumurra, Western Australia.

Treatment Capacity: 150EP, 46m3/day.

Date Commissioned: May 2011.

Operational Status: De-commissioned - Plant closed May 2014.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 14 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and was not seeded.  The process was producing compliant final effluent within 30 days.