Sewage Treatment

Sinclair Village

Project: Sinclair Village Waste Water Treatment Plant.

Location: Leinster Western Australia.

Treatment Capacity: 200EP, 62m3/day.

Date Commissioned: April 2010.

Operational Status: De-commissioned - Plant closed May 2013.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 16 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and the process was producing compliant final effluent within 30 days