Sewage Treatment

Lochada Village

Project: Lochada Village Waste Water Treatment Plant.

Location: Perenjori, Western Australia.

Treatment Capacity: 300EP, 93m3/day.

Date Commissioned: April 2010.

Operational Status: De-commissioned - Plant closed December 2012.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 16 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and the process was producing compliant final effluent within 30 days.