Sewage Treatment

Karara Mine

Project: Karara Mine Waste Water Treatment Plant.

Location: Karara, Perenjori Western Australia.

Treatment Capacity: 60m3/day.

Date Commissioned: June 2010.

Operational Status: Currently operating.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 14 days from mobilisation to commissioning.

This plant was designed specifically to address the proportionally high influent nitrogen and sporadic loading associated with “non-accommodation” waste water applications.

The plant was commissioned with influent sewage and seeded from the Karara Village Plant 1.  The process was producing compliant final effluent within 30 days.