Sewage Treatment

Hope Downs Sth Plant 2

Project: Hope Downs South Village Waste Water Treatment Plant 2.

Location: Hope Downs, Western Australia.

Treatment Capacity: 300EP, 93m3/day.

Date Commissioned: December 2006.

Operational Status: Currently operating.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 14 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and was seeded from the adjacent Plant 1.  The process was producing compliant final effluent within 10 days.