Sewage Treatment

Cape Lambert Village "B"

Project: Cape Lambert Village “B” Waste Water Treatment Plant.

Location: Cape Lambert Accommodation Village, Pilbara, Western Australia

Treatment Capacity: 1200EP, 372m3/day.

Date Commissioned: June 2013.

Operational Status: Currently operating.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 20 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and seeded from the adjacent Cape Lambert Village “A” Plant. The process was producing compliant final effluent within 7 days.

Treated effluent specification requires Total Phosphorus < 1mg/L and Total Nitrogen <10mg/L .