Sewage Treatment

Cape Lambert EPCM

Project: Cape Lambert Port EPCM Waste Water Treatment Plant.

Location: Cape Lambert Port, Pilbara, Western Australia.

Treatment Capacity: 50m3/day.

Date Commissioned: January 2012.

Operational Status: De-commissed - Plant closed February 2015.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 17 days from mobilisation to commissioning.

The plant was commissioned with influent sewage and seeded from the Cape Lambert Village “A” Plant.

This plant was designed specifically to address the proportionally high influent nitrogen and sporadic loading often associated with “non-accomodation” waste water applications. Treated effluent specification required Class A water for reuse.

The process was producing compliant final effluent within 7 days.