Sewage Treatment

Brockman 4 Village

Project: Brockman 4 Village Waste Water Treatment Plant.

Location: Brockman 4 Village, Pilbara, Western Australia.

Treatment Capacity: 1400 EP, approximately 434m3/day.

Date Commissioned: July 2008.

Operational Status: Currently operating.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 18 days from mobilisation to commissioning.

The plant was commissioned with influent sewage, without seeding, and was fully compliant within 30 days of commissioning.