Sewage Treatment

Brockman 4 Central

Project: Brockman 4 Central Facilities.

Location: Brockman 4 Mine, Pilbara, Western Australia.

Treatment Capacity: 32kL/day.

Date Commissioned: December 2013.

Operational Status: Currently operating.

Comments: This plant was Factory Acceptance Tested prior to shipment to site.

Site construction time was 14 days from mobilisation to commissioning.

The plant was commissioned with influent sewage, without seeding, and the final effluent was compliant within 30 days of commissioning.